SAP C_TS422_2021 Certification Sample Questions and Answers

Get C_TS422_2021 Dumps Free, and SAP S/4HANA Production Planning and Manufacturing PDF Download for your SAP S/4HANA Production Planning and Manufacturing Certification. Access C_TS422_2021 Free PDF Download to enhance your exam preparation.The SAP S/4HANA Production Planning and Manufacturing Certification Sample Question Set on this page is designed to familiarize you with the actual SAP C_TS422_2021 exam format and question types. These basic sample questions help you understand the structure of the test and what to expect. While these questions provide a good starting point, they are just a glimpse of the real exam scenario. To get familiar with more exam properties, we suggest you try our Sample SAP S/4HANA Production Planning and Manufacturing Certification Practice Test.

This Sample SAP C_TS422_2021 Certification Practice Exam is intended for evaluation purposes only. If you are planning to take the SAP Certified Associate - SAP S/4HANA Production Planning and Manufacturing and want to thoroughly test your SAP S/4HANA knowledge to identify any weak areas, we strongly recommend starting your preparation with our Premium SAP S/4HANA Production Planning and Manufacturing Certification Practice Exam. Our premium practice tests offer an extensive set of scenario-based questions that closely simulate the actual exam environment. By using our premium SAP S/4HANA Production Planning and Manufacturing exams, you can ensure comprehensive coverage of all necessary topics, significantly boosting your confidence and increasing your chances of success on your certification exam.

SAP S/4HANA Production Planning and Manufacturing Sample Questions:

01. How can Production Planning and Detailed Scheduling (PP/DS) enhance the standard planning functionality?
Please choose the correct answer.
a) By providing multilevel material requirements planning
b) By providing future demands from demand figures in the past
c) By providing cross-plant planning and deployment
d) By providing replenishment proposals with exact times
 
02. Which technological advances enabled the development of SAP S/4HANA as the digital core?
There are 3 correct answers to this question.
a) Big and affordable memory
b) Multi core processors enabling parallelism of tasks
c) Wide adoption of web standards such as Service oriented architecture
d) Advances in the three-tier architecture approach
e) Capability to add to server landscape and scale
 
03. Which of the following apply to MRP Live?
There are 2 correct answers to this question.
a) The BAdIs for classical MRP also apply to MRP Live.
b) The definition of the planning scope is more flexible.
c) The sequence of planning materials is calculated across plants.
d) Planned orders need to be converted to purchase requisitions for externally procured materials.
 
04. The settings for MRP can be maintained at different levels. If settings have been maintained in different places, in which sequence does the system search for the MRP settings?
Please choose the correct answer.
a) MRP Group –> Material Master –> Plant Settings
b) Plant Settings –> MRP Group –> Material Master
c) Material Master –> Plant Settings –> MRP Group
d) Material Master –> MRP Group –> Plant Settings
 
05. Which elements are included in the structure of the batch where-used list?
There are 3 correct answers to this question.
a) Purchase orders
b) Planned orders
c) Transfers from batch to batch
d) Stock transfers
e) Collective orders
 
06. The procurement type of your material is set to "E" for In-house production. Which of the following is valid to determine a source of supply in SAP S/4HANA?
Please choose the correct answer.
a) Production Version
b) Selection Method
c) Contract
d) Purchasing Info Record
 
07. For which categories can you define bills of materials (BOMs) in SAP S/4HANA?
There are 2 correct answers to this question.
a) Sales Order
b) Document Structure
c) Class
d) Work Center
 
08. You want to procure your material components based on a forecast for the finished material derived from historical sales. When customers order, you produce the finished product and reserve it for that particular order.
Which is the appropriate planning strategy to use?
Please choose the correct answer.
a) 50 Planning without final assembly
b) 20 Make to order production
c) 30 Production by lot size
d) 40 Planning with final assembly
 
09. A customer is considering switching from order-related settlement to product-related settlement. What are capabilities of cost collectors?
There are 2 correct answers to this question.
a) They can be created automatically during month end process.
b) They can be applied to make-to-stock production order.
c) They can be used for manufacturing with collective orders.
d) They can be used for repetitive manufacturing.
 
10. Which warehouse management functions are available in SAP EWM but NOT in SAP WM?
There are 3 correct answers to this question.
a) Handling Unit Management
b) Expected goods receipt
c) Labor Management
d) Yard Management
e) Slotting
 

Quick Tips:

  • SAP includes a note: "There are 'N' correct answers to this question" in the actual SAP S/4HANA PP Certification Exam.
  • SAP does not ask "True or False" type questions in the actual SAP C_TS422_2021 Exam.
  • SAP provides an option to increase (+) or decrease (-) the font size of the test screen for better readability in the actual SAP Certified Associate - SAP S/4HANA Production Planning and Manufacturing Exam.

Solutions:

Question: 01

Answer: d

Question: 02

Answer: b, c, e

Question: 03

Answer: b, c

Question: 04

Answer: d

Question: 05

Answer: a, c, d

Question: 06

Answer: a

Question: 07

Answer: a, b

Question: 08

Answer: a

Question: 09

Answer: b, d

Question: 10

Answer: b, c, e